18/5/08
Ng123 Test
Run
On
Saturday 17/5/08 Ng 123 was lit up and prepared for a test run up the line to
WVJ station to ensure all is working correctly. After some minor adjustments at
the Mussel Pool depot, Ng123 moved off to Mussel Pool yard and then proceeded to
WVJ where it was turned on the turntable before returning after several journeys
up and down the Mussel Pool branch, to the depot.
 |
 |
 |
 |
| Ng123 prepares to
depart Mussel Pool station |
Climbing
away from Bennett Brook Bridge |
Approaching the WVJ
distant signal |
Ng 123 is
currently the only steam locomotive operational in W.A.
Shunting the V van from the turntable approach road as
Rosalie departs on the service train |
On the turntable
|
Returning to Mussel Pool. |
15/5/08
Ng123
Passed "In Steam" Boiler Inspection
On Tuesday
13/05/08 Ng123 was lit up for a visit by our Boiler Inspector. The boiler was
certified as fit for use after inspection at 5pm. Shortly after a test run was
made down to the Mussel Pool yard before stabling the loco. A good test run will
likely occur over this coming weekend to ensure Ng123 is ready for use on
Friends of Thomas Day on Sunday 25th of May.
Thanks to
Jamie, Bob, Neil, Derek and Brian for their efforts this day.
Both Safety Valves lifting during testing |
Test running |
Live steam returns to the BBR loco shed |
11/5/08
A busy
week at BBR this week with members pitching in to get jobs done.
Early in
the week on the Monday, Simon took delivery of the Perry wheel sets on their
return from Gemco. Derek and Neil were out on Tuesday afternoon to meet the
boiler inspector for Ng123's "Open Inspection". All went well enabling
preparations to be made for what would be a busy Friday night.
BT1 Re-profiled wheels |
Ng123 open inspection |
Michael driving Planet #2 |
On
Thursday Planet #2 moved under its own power for the first time at BBR, since
being regauged from 3ft 6inch (which it had been converted to by the Boulder
Loop Line group), back to its original 2ft gauge. Michael reports that although
there is still much to be done with electrical needs, the loco can be operated
mechanically. This he duly showed all in attendance on the following Friday
evening.
Friday
afternoon came around and approx 15 members were in attendance to "Box
Up" Ng123. Thuis meant fitting the Dome, Manhole cover, all washout plugs,
tender manhole covers, gauge glasses and safety valves. The crew worked hard to
have the locomotive mostly finished by around 8pm, ready for lighting up the
next day and to break for dinner. After dinner loose ends were completed on
Ng123 whilst efforts were directed towards refitting more of BT1's boiler
cladding.
A collage of Friday night activity working on steam
engines |
Ng123 is hauled out of the loco shed for steam testing |
Smoke drifts as the loader is coaling 123 |
Newly painted cladding being fitted to BT1 |
Saturday
was another organised work day primarily to steam test Ng123. About 13 members
plus the train crew were on site for the day. Preparations were made to light up
123 after a good shower of rain had passed around 9am. When ready, the fire was
lit around 11am. Whilst waiting for pressure to build further work was carried
out on BT1 with most of the cladding being added. Once working pressure was
achieved on 123, the safety valves were set and inspections made of all other
fittings. All went well with only a couple of minor leaks which require
attention. Pleasingly, the Dome and the manhole cover had not even a wisp of
leaking steam. It is not fun when you have to undo all those bolts and try
again.
With a
successful steam test, Ng123 will now be steamed again on Tuesday where it will
undergo its "In Steam" inspection by the boiler inspector. It is quite
likely that Ng 123 will then be test run the following weekend.
4/5/08
Pw27 Wyndham leaving Mussel Pool |
The Train Crew for the Sunday 4/5/08 |
And in the station looking after our customers was
Julie and Luke |
Sunday
4/05/2008 was a beautiful Autumn day, the pictures above show the 4 coach
service train for the day, hauled by PW 27 and the well turned out crew for the
day. The Mills family making up 5 out of the 8 members operating the railway,
with longstanding members Bob and Richard training new member Ken.
Neil and Derek in the firebox of NG123 about to reset the brick arch
into place |
Liam, Peter, David, Ross, Derek and Richard working on the steam
engines |
Michael working on Planet #2 |
The Friday
night crew continue to progress with jobs needing to be done around the depot.
Now that the track upgrade is over, we can concentrate on getting some jobs done
on the motive power fleet.
With FOTTE
Day looming fast, there is now a rush on to get NG123 ready for steaming. A
cleaning of the loco was done by Liam and his Dad Peter, whilst David checked
over the bolts inside the smokebox. Neil and Derek were to be found inside the
firebox repositioning the centre brick of the Arch which had been slightly
dislodged during last years steam season. Not the easiest job around!
Unfortunately
BT1 will not make it to Thomas day this May as we are still waiting for return
of the wheels from re-profiling, never mind the need to put it all back together.
Reconstruction has started though, with Richard and Ross getting the first
section of boiler cladding in place. The tanks have been painted and are ready
to be installed. All axle boxes have been re-metalled and await fitting to the
axles.
Meanwhile
Michael spent the evening working on some gaskets and other fittings on Planet
#2. All of the air line work has now been completed on this loco and even the
air whistle works. Now the electrics need to be sorted out and then decisions will
need to be made about the cab arrangements and drawgear.
Keep up
the good work everyone
26/4/08
Today the
Western Australian Light Railway Preservation Association celebrates its 32nd
Birthday and the Bennett Brook Railway will have been running for 24 years.
Bobs Track
Report
During the
week just gone, the midweek guys cut another 140 sleepers which were required to
finish the track upgrade project, stacked them and delivered them on site. In
fact there are a further 59 spare sleepers which have been stacked on the track
panels near the pit shed entry track. These are however ear-marked for use.
The Midweek crew and the last load of timber sleepers
on the QBB, prior to dropping line side. |
During the week, 3 of BBR's goods wagons could be
found stowed on 3 different tracks at WVJ station. |
The train
crews had fun running different configurations to work around the track crews.
We had WVJ - MP; KF - MP, WVJ - Zamia via KF and WVJ - Zamia south.
The
Skilled Rail crews have all but finished, except for about 100 sleepers which
will be done on Monday. The areas not yet completed are
:Wig Wag xing to KF,
these were missed on the initial drop. (24 sleepers). 3 road WVJ Nth to 2 Trees
(top of the grade north of WVJ), 50 woods & 10 steels required. WVJ to
Beechboro Rd - 15 woods & 5 steels required.
This is
the end of this part of the project for Skilled. However they will be back in a
few weeks to replace some point timbers at KF west and 2 road south at WVJ .
This cannot be done until the sleepers required have been measured and
"Tamper Dave" cuts them.
Currently
the section from Mussel Pool to WVJ has been cleared for track speed of 20kph,
however there are still speed restrictions in place on the loop until tamping
can take place. This will most likely occur on Wednesdays and Thursdays as these
are the days that the mid-week crew are at the railway. The midweek crew have
gotten quite good lately at tamping and are happy to continue to do so.
A big
thankyou must be given to Derek, Bob, Jamie, Tamper Dave, Pommie Dave and all of
the Midweek and Friday Night Crews who have worked tirelessly to ensure the
smooth completion of the track work project. There is still much to be done
though, as now we have to finish the tamping and the clean up of removed timber
sleepers. Thank you to all members involved, and a please help out if you can,
to any other members, to help finish the clean up.
Parkers
Siding Named
On Sunday
19/04/08 about 20 BBR members gathered for the monthly General Meeting of the
organisation at the Revolutions Museum, Boardroom. After getting the official
business completed the meeting adjourned to WVJ station to catch the last train
service to Mussel Pool station where the official naming ceremony for
"Parkers Siding" took place. The name board was painted and installed
by K Wright, and Ross was on hand to receive recognition for his efforts.
Parkers
Siding is named after long standing BBR member Ross Parker who has done much
around the railway over many years. Ross undertook the relocation and
construction of the Goods Shed and built the associated track work at Mussel Pool to
provide the railway with this most useful facility. After much organisation and
sourcing of materials, the project started to take shape during 1995 and was
completed in October 1997. Later Ross also restored to working order and
installed the 1855 A&J Inglis goods crane on the loading dock at the goods
shed. This completed Mussel Pool station, providing the area with an appropriate
Goods Shed facility.
After the
brief ceremony, members took the opportunity to socialise and have a chat with
Ross at Mussel Pool and then the group reboarded the train, travelling to WVJ
where a sausage sizzle and drinks was held.
Kieran waits to unveil the name board at the ceremony
whilst Bob and Ross tell the story of the Good Shed facility
|
Ross (left) and Bob under the unveiled name board.
|
Members socialised after the ceremony
|
then gathered at WVJ's platform 2 Subiaco
building for a sausage sizzle
|
The
locomotive watering tank project is now going to go ahead as Ross has agreed to
manage this project. The tank itself has been in storage at the Mussel Pool depot for
some time. Also in storage is a water column which was acquired by the
organisation from Gnowangerup in May 1992 along with a tank mounted column from
Formby siding. These are hoped to be put into use in conjunction with the water
tank.
19/4/08
A busy
week has passed at the BBR with the "Skilled Rail" track crew making
good progress, replacing all sleepers (approx 400) in the WVJ to Zamia section.
A record number of sleepers were replaced on the Tuesday with 182 being recorded
as removed and inserted, spiked / clipped. Due to such good progress, it has
been decided that the project will be extended for another week and go ahead and
hopefully complete the section from Zamia to Kangaroo Flats. Thus a further 380
sleepers were required to be provided for the job. The 150 steel sleepers needed
were loaded onto the QBB on Wednesday afternoon and were dropped line side on
Thursday morning by the Skilled crew. 230 timber sleepers are needed and so the
BBR midweek crew got busy and commenced cutting these to size from the stock
pile. By Friday, 150 sleepers had been sorted & sized. These were finished
and stacked by the Friday night crew and then loaded onto the QBB for dropping
in the Zamia - Kangaroo Flats section on Monday morning. The remaining sleepers
are to be cut during the week to come.
Add to all
of that - the railway has also provided train services every day to the
travelling public for the 1st week of the school holiday period. These trains
have been operating Mussel Pool to Kangaroo Flats only in "Top and
Tail" formation with Wyndham and the Planet #1. With Ashley in use on the
works train and Rosalie on the sleeper train, we have had all of our operating
diesel motive power in traffic during the week
The sleeper train combines with the service train at
Kangaroo Flats to ease safe working requirements |
The midweek crew cutting sleepers on the BBR sawmill |
The QBB loaded with 150 timber sleepers at the end of
Friday night |
13/4/08
More Track
- A week of track work notes by Bob Baker.
Tuesday
Tamper Dave and Bob laid ballast from the ballast crossing east of Kangaroo
Flats to Kangaroo Flats west points on the main line.
On
Wednesday and Thursday, Tamper Dave and the midweek crew tamped the line from
the ballast crossing east of Kangaroo Flats to Kangaroo Flats west points on the
main line. A great effort. Bob had to run the revenue train service on Wed and
Thurs as Terry was ill.
Thursday
morning Barry repaired the air leak in the Planet.
On Tuesday
the crane broke down on the way up to Kangaroo Flats and on Friday it refused to
start. Jamie later repaired the crane
Friday
Dave and Bob delivered ballast to the loop at Kangaroo Flats.
So far an
estimated 893 sleepers have been replaced up until Thursday afternoon.
Mussel
Pool line is completed including tamping; Sleeper replacement completed from the
old Ballast Crossing east of Kangaroo Flats thru the rally road Wig Wag
crossing, including the Kangaroo Flats Loop. Tamping has been completed between
the old Ballast crossing and the Kangaroo Flats main line west points.
At
Whiteman Village Junction, the yard is complete including tamping. Sleepers have
been replaced from WVJ South to part way up the long straight to a short
distance beyond the top of Robert's Bank.
Next week
Skilled will continue south towards Zamia and tamping will begin on the section
also.
And just
for something different - whilst delivering a load of Ballast to Whiteman
Junction the truck delivering the load, got itself bogged when venturing a
little too far off the dirt track. The photo below was captured by Bob when all
assistance was mustered, and a interesting collection of tractors was used to
drag the truck out of the dirt.
A further
100 timber sleepers were dropped by the small group of members who showed up for
the Friday night crew, from the middle of the S bends through to the Zamia side
of the level crossing at Contractors Corner. 30 steel sleepers were also dropped
from the top points at the north end of WVJ through to the 2 trees at the top of
the grade.
5/4/08
Track
Track Track
Track work
is the current news on the BBR. After a few minor delays, works began on our
track upgrade by Skilled Rail Services. Members Bob, Jamie and Dave have been at
the railway each working day to ensure a BBR presence, liaise with the work
crews, provide drivers for locomotives & provide transport and move
equipment, as well as operate the tamper and drop ballast.
Gemco
"Wyndham" is mostly being used as motive power for the ballast work
using the LA hopper wagon and D van to transport tools etc. "Ashley"
is being used to move the air compressor "Blowhard" and provide crew
transportation with one ADL coach. Blowhard provides the track crew the ability
to use air operated tools to make the work easier.
Works trains in the platform at Mussel Pool station |
Ashley with Blowhard out on the line |
Skilled workers use the Air Drill to spike sleepers |
Tamper Dave at work on BBR's tamper |
The Mussel
Pool to WVJ section has been completed and awaits inspection by the track master
to enable lifting of the imposed 10kph speed restriction, to return to line
speed. The yard / platform roads at Whiteman Junction are currently almost
complete with some ballasting to do. The crew are still at work in the Junction
to Kangaroo Flats section.
Derek and Tony prepare for a departure to drop steel
sleepers |
Derek prepares to drop another sleeper as the upper
quadrant signal clears to green for our train approaching Zamia station |
On Friday
evening 4/04/08 the night crew dropped a further 200 steel "Straight"
sleepers (those used on the straights) in the southern loop section from the top
of Roberts Bank through to Zamia and then beyond to Emu Way. This completes the
current drop of steel sleepers with all of the remaining "Curve"
sleepers required having been dropped the previous week. We now only need to get
the remaining timber sleepers cut and dropped between the S bends and Zamia.
Any
members not already involved in the track upgrade project are requested to help
out even just a little bit to ease the load for some others who are wearing
out.
A big
thank you to all who are involved in this very important project. There is still
quite a bit to do so "keep up the good work".
Cab being relocated |
Ng123 with Gemco and Planet |
Other jobs
done involved further preparation of timber sleeper which were stacked and
loaded onto the QBB for next Friday. The work train was also restocked with
extra steel & timber sleepers. Ng123 was dragged out of the shed to enable
access to BT1's side tanks which are soon to be painted before refitting to the
locomotive. The tanks were lifted from the rear of the loco shed and placed
outside for loading onto a truck to be taken off site. This also involved
relocating the cab.
Click here for
Archived News Feb -Mar 2008